MTR uses skidding method to build Hung Shui Kiu Station over live tracks

MTR Corporation is building the new Hung Shui Kiu Station using a skidding method, a world first for a heavy-rail project. The technique involves assembling structures off-site and sliding them into position over an operating Tuen Ma Line viaduct, with targeted completion by 2030.

MTR uses skidding method to build Hung Shui Kiu Station over live tracks

MTR Corporation is using a skidding method to build the new Hung Shui Kiu Station over a busy, operating Tuen Ma Line viaduct, marking the method's first application to a heavy-rail project worldwide. Skidding involves moving a heavy structure along a controlled sliding system into a designated position.

Located between Tin Shui Wai and Siu Hong Stations, the station is a key railway infrastructure project for the Northern Metropolis. Upon its targeted completion in 2030, it will link with the Hong Kong-Shenzhen Western Rail Link and a Smart and Green Mass Transit System in the Hung Shui Kiu/Ha Tsuen Development Area to form a strategic three-line cross-boundary transportation hub.

Alan Yan Wai-ming, MTR Head of Project Delivery (New Territories South), said the team faced two main challenges during planning: keeping the operating environment for the Tuen Ma Line reliable while minimising disruption to passengers. He noted that traditional major work near tracks is carried out during the limited overnight service break, known as the “golden two hours.” Building the station above live tracks within that window would pose considerable safety risks and could stretch construction over many years.

“We had to think outside the box, and seek a completely new feasible solution to turn ‘mission impossible’ into ‘mission possible’,” Yan said. The team studied skidding techniques used in mainland China and Europe, including methods for moving historic buildings and oil platforms. The approach for Hung Shui Kiu Station involves building the structures beside the railway first, then skidding them into the future station position.

While foundation works proceed at the site, components prefabricated off-site are being assembled in work areas about 30 metres away from either side of the viaduct. The project involves two large station structures, each approximately 210 metres long, 15 metres wide and 20 metres high. Once ready, each structure, weighing about 10,000 tonnes – equivalent to the weight of 100 blue whales – will be lifted slightly by synchronised hydraulic jacks and moved along straight guide tracks into position.

Lawmaker Aaron Bok Kwok-ming said skidding was the only feasible and cost-effective way to retrofit a station onto an existing operational line. He said assembling the platform structures at ground level before moving them into place would reduce the risks associated with prolonged heavy lifting beside a live, electrified viaduct. Foundation work at the site is largely complete, and about a quarter of the platform structure for trains heading towards Wu Kai Sha is already taking shape.

MTR is relying on off-site prefabrication and Modular Integrated Construction to speed up construction without compromising safety. Yan said using prefabricated components is safer because they are produced in a factory assembly-line environment, allowing for closer quality checks. Engineers use Building Information Modelling (BIM) to create a detailed 3D model of the station, and QR codes help identify and track components on site.