Hong Kong waste plant fire delays full operations, repairs underway
A fire at Hong Kong's I.PARK1 waste treatment facility on October 26, 2026, damaged the third incineration module. The government says full operations will be delayed, with repairs ongoing. Only modules one and two have resumed testing. Fire investigators ruled out electrical fault, arson and chemic
The Hong Kong government has confirmed that a fire at the Integrated Waste Management Facility Phase 1 (I.PARK1) on 26 October 2026 will delay its planned full commissioning within the year. The fire, which broke out at around 12:40 pm on the roof of the third incineration module, was largely extinguished by about 4:45 pm the same day.
According to a Legislative Council reply on 18 November, the fire affected only the third module's upper and roof areas, including aluminium sheeting, steel roof supports, ventilation ducts and pipes. The incineration systems on the middle floors sustained only minor damage. The adjacent modules one and two, as well as the waste storage bunker and tipping hall, were unaffected.
The Fire Services Department concluded its investigation, ruling out electrical failure, arson and spontaneous combustion of chemicals. The likely cause is either welding work or smoking. The contractor has engaged a registered structural engineer to assess damage and prepare a repair plan; no completion date has been set.
Before the fire, I.PARK1 had processed about 390,000 tonnes of municipal solid waste since December 2025, with daily processing gradually rising to about 1,900 tonnes in October. The three modules entered system testing and trial operation in December 2025, March 2026 and July 2026 respectively. The facility had essentially reached its design capacity of 3,000 tonnes per day on 23 October, just three days before the fire.
Under the contract, the contractor is responsible for all repairs before formal handover and has arranged 'Contractor's All Risks' insurance covering fire damage. The Environmental Protection Department (EPD) confirmed that modules one and two were inspected and deemed safe to restart; they resumed system testing on 30 October. Waste originally destined for I.PARK1 has been redirected to the West New Territories Landfill extension.
The EPD said it has ordered all facility contractors to review fire-prevention measures, enforce a strict hot-work permit system, ban smoking on site, and conduct fire drills. Since January 2026, the I.PARK1 contractor has expelled nine workers caught smoking on site and fined subcontractors 59 times, totalling about HK$810,000. The government said it will hold a safety-sharing session in November 2026 to promote safe construction and operation practices across all EPD-managed waste facilities.